Client |
Voest Alpine (Sandvik Materials Handling) |
I |
Location |
AMC, Henderson WA |
| |
Completion |
2005 |
|
|
|
|
|
| Voest Alpine 8000 to 9000t p/h shiploader - Rio Tinto Iron Ore major project |
| Supply, fabricate, surface treat and deliver to AMC Henderson, erect to dry commissioning and load out on heavy lift ship. |
| Shiploader SL2P was fabricated and surface treated at PIC Naval Base workshops and transported in several oversize configurations to AMC-CUF Henderson for full assembly and dry commissioning, before shipping in full working order to Dampier Port via the heavy lift ship "Big Lift". It was then installed on the wharf ahead of wharf completion in May 2005. |
| The project was completed ahead of time and on budget. |
| back to projects list >> |