Woodside Chimneys

ClientWoodside Petroleum

LocationKarratha, WA

SectorMining & Resources

Supply, fabrication, surface treatment of Gas Turbine Emission Stacks (GTES), ie GTES 4007, 4008 and 1410, also Thermal Combustion Unit. Units varied but generally were 40 metres high x 6 metres ID in 2 pieces of 20 metres long of bolted flange construction.

Work included access towers, stairways, landings, hand rails, 60,000 refractory anchors and management of refractory installation prior to shipment. Shipping weights of approximately 190 tonnes each were involved.

TCU combustion chamber was 100% stainless steel 316 material. Construction templates were also part of the contract for foundation bolts.

All works were successfully completed safely on time and on budget.